Managed By:

© 2020 Pennsylvania Department of Transportation. All rights reserved.

422improvements.com

PROGRAM INFORMATION

U.S. 422 IN VALLEY FORGE

Status of the Project: Ongoing

Construction Started: Summer 2016

Construction Completion Date: May 2020

Cost: $97,400,000, funded through ACT 89

General Contractor: JBC Associates, Inc.

PROJECT UPDATE - November 2019

Construction activities continue to advance on U.S. 422 between the Route 363 (Trooper Road) and First Avenue interchanges for the $97.4 million transportation improvement project.

The Contractor has completed constructing the new abutment and piers for the east bound structure over the river.  All five (5) beam segments have been placed as of mid-November.  Concrete placement for the remaining sections of the bridge deck are scheduled for the remainder of this year and is weather dependent.

Completing the roadway connections to the completed bridge structure will follow the completion of the bridge decking.  Construction of the final sound barriers and the completion of the Upper Merion Trail (Schuylkill River West Trail) retaining wall.  This will facilitate trail traffic under the River Bridge.  The trail will remain closed until Upper Merion Township has completed their section of trail construction, located adjacent to the retaining wall now under construction.

​The traffic on U.S. 422 will be staying in the current configuration until May 2020.  The project is on-track to complete construction at that time.

PROJECT DESCRIPTION

The improvements to U.S 422 in the area of Valley Forge

consist of four separate projects involving the replacement or

rehabilitation of five (5) bridges to improve multi-modal travel and

reduce congestion between the Route 363 (Trooper Road) and

Route 23 (Valley Forge Road) and First Avenue interchanges. 

 

The focal point of this program is the replacement and expansion of

five (5) U.S. 422 bridges and the widening of one mile of U.S. 422

between the Route 363 and Route 23 interchanges.  Additional project

elements are noted below.  Each day 92,000 vehicles travel on

U.S. 422’s four-lane structures in this area, along with pedestrians

and bicyclists who used the protected path alongside the highway’s eastbound lanes to cross the Schuylkill River. With the amount of crossings and important cultural attractions, office park areas and recreational amenities in the area, congestion in this section is a frequent occurrence.

 

Important additional project elements include:

 

  • Re-designed concrete pavement

  • Sound barrier wall

  • Two (2) retaining walls required due to the widening of the roadway

  • Drainage improvements

  • ITS (Intelligent Transportation System) connections allowing for the integrated use of technology for the assessment of vehicle movement, motorists alerts, queue detection, etc.

​​

This section of the U.S. 422 improvements is known as the Schuylkill River Crossing Complex.  With an estimated construction cost of $100 million, construction bids were opened on November 5, 2015, and construction commenced in late 2016.  The project was accelerated by the passage of Act 89, which provided the critical funding.

 

 The following project elements have been completed:

 

  • Westbound structure of the Schuylkill River Bridge (SRB) has been completed.  Eastbound traffic has been routed onto the new bridge while removal and reconstruction the eastbound bridge takes place.

  • The U.S. 422 eastbound off-ramp at Route 23 (fly over) has been completed.

  • The rehabilitation of the Route 23 bridge is completed.

PHOTOS
LATEST PRESS RELEASES
logo-padot.png